Damon BESS
BetaActiveBatteryERCOTLBNL
4.98 MW storage in Brazoria, TX · Proposed COD February 2025
4.98 MW
Capacity
1
Components
Battery
—
In Queue
IA Executed
IA Status
Signed Oct 2022
Interconnection Timeline
IA → COD
2y 4m
Schedule
14 months past proposed COD
Construction75%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 18, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-02-03
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
Baccharis Storage LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Station Name: DA Load/Load Transformer Name: TR1 PTI BUS number: 42370 Voltage in kV (Transmission Level): 138 kV
Data Source
LBNL
No news available for this project.