Ardesia Storage
BetaActiveBatteryERCOTLBNL + Live
100 MW storage in Caldwell, TX · In queue since June 2022 · Proposed COD June 2027
100 MW
Capacity
1
Components
Battery
3y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5 years
Facilities Study50%
Queue EntryJun 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-25
Project Details
State
TX
County
Caldwell
Region
ERCOT
Developer
Ardesia Storage Project LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 7325 Mendoza - 7216 Lockhart
Data Source
LBNL + Live
No news available for this project.