Fort Mason BESS — Project Summary

Queue ID
ERCOT-23INR0500
Capacity
9.8 MW
Technology
Battery
Status
active
Location
Mason, TX
Region
ERCOT
Developer
Regis Mason LLC
IA Status
IA Executed

Fort Mason BESS

BetaActiveBatteryERCOTLBNL

9.8 MW storage in Mason, TX · In queue since August 2023 · Proposed COD March 2025

9.8 MW

Capacity

1

Components

Battery

2y 7m

In Queue

IA Executed

IA Status

Signed Jan 2023

Interconnection Timeline

IA → COD

2y 2m

Total Duration

2y 7m

Schedule

13 months past proposed COD

Construction75%
Queue EntryAug 18, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 10, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-03-04

Project Details

State

TX

County

Mason

Region

ERCOT

Developer

Regis Mason LLC

Utility

Entity

ERCOT

Point of Interconnection

Station Name (TDSP Station Code): FORTMA; Load/Load Transformer Name: T1-FM140; PTI BUS number: 76390; Voltage in kV (Transmission Level): 138kV Transformer: 3x 4000kVA 800VAC - 12.47kVA

Data Source

LBNL

No news available for this project.