Laureles BESS
9.8 MW storage in Cameron, TX · In queue since October 2022 · Proposed COD June 2025
9.8 MW
Capacity
1
Components
Battery
3y 5m
In Queue
IA Executed
IA Status
Signed Feb 2023
Queue → IA
4 months
IA → COD
2y 4m
Total Duration
4 months
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-06-21
State
TX
County
Cameron
Region
ERCOT
Developer
Regis Laureles LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Station Name (TDSP Station Code) LAURELES; Load/Load Transformer Name LD01; PTI BUS number 5756; Voltage in kV (Transmission Level) 138kV
Data Source
LBNL