Laureles BESS — Project Summary

Queue ID
ERCOT-23INR0499
Capacity
9.8 MW
Technology
Battery
Status
active
Location
Cameron, TX
Region
ERCOT
Developer
Regis Laureles LLC
IA Status
IA Executed

Laureles BESS

BetaActiveBatteryERCOTLBNL

9.8 MW storage in Cameron, TX · In queue since October 2022 · Proposed COD June 2025

9.8 MW

Capacity

1

Components

Battery

3y 5m

In Queue

IA Executed

IA Status

Signed Feb 2023

Interconnection Timeline

Queue → IA

4 months

IA → COD

2y 4m

Total Duration

4 months

Schedule

9 months past proposed COD

Construction75%
Queue EntryOct 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 16, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-06-21

Project Details

State

TX

County

Cameron

Region

ERCOT

Developer

Regis Laureles LLC

Utility

Entity

ERCOT

Point of Interconnection

Station Name (TDSP Station Code) LAURELES; Load/Load Transformer Name LD01; PTI BUS number 5756; Voltage in kV (Transmission Level) 138kV

Data Source

LBNL

No news available for this project.