Brightside Solar Alt POI
ERCOT-23INR0487BetaActiveSolarERCOTLBNL + Live
50 MW generation in Live Oak, TX · In queue since May 2022 · Proposed COD August 2026
50 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Status
Signed Jun 2020
Interconnection Timeline
IA → COD
6y 2m
Total Duration
3y 11m
Construction75%
Queue EntryMay 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 11, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-08-14
Project Details
State
TX
County
Live Oak
Region
ERCOT
Developer
Brightside Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8156 Charter Substation 138kV
Data Source
LBNL + Live
No news available for this project.