Taormina Storage
ERCOT-23INR0479BetaActiveBatteryERCOTLBNL + Live
231.86 MW storage in Bexar, TX · In queue since April 2022 · Proposed COD May 2029
231.86 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 1m
Facilities Study50%
Queue EntryApr 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-26
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
Taormina Storage Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV VH Braunig (5025) to Valley Road 138kV (5465)
Data Source
LBNL + Live