Sepanta Solar
217.26 MW generation in Nolan, TX · In queue since October 2022 · Proposed COD September 2029
217.26 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-18
State
TX
County
Nolan
Region
ERCOT
Developer
BREG - Belgian Renewable Energy Group
Utility
—
Entity
ERCOT
Point of Interconnection
1339 ESKOTA_9 138kV (PSS/E BUS #1339, Station Name: ESKOTA_8, kV: 138 kV) Property is adjacent (West) to the Oncor Sweetwater Eskota Switch #1339. POI would simply be on the other side of the fence of the switch.
Data Source
LBNL + Live