Sepanta Solar — Project Summary

Queue ID
ERCOT-23INR0473
Capacity
217.26 MW
Technology
Solar
Status
active
Location
Nolan, TX
Region
ERCOT
Developer
BREG - Belgian Renewable Energy Group
IA Status
Facility Study

Sepanta Solar

BetaActiveSolarERCOTLBNL + Live

217.26 MW generation in Nolan, TX · In queue since October 2022 · Proposed COD September 2029

217.26 MW

Capacity

1

Components

Solar

3y 5m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

6y 11m

Facilities Study50%
Queue EntryOct 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-18

Project Details

State

TX

County

Nolan

Region

ERCOT

Developer

BREG - Belgian Renewable Energy Group

Utility

Entity

ERCOT

Point of Interconnection

1339 ESKOTA_9 138kV (PSS/E BUS #1339, Station Name: ESKOTA_8, kV: 138 kV) Property is adjacent (West) to the Oncor Sweetwater Eskota Switch #1339. POI would simply be on the other side of the fence of the switch.

Data Source

LBNL + Live

No news available for this project.