Ophelia Solar — Project Summary

Queue ID
ERCOT-23INR0471
Capacity
110.5 MW
Technology
Solar
Status
active
Location
Ector, TX
Region
ERCOT
Developer
Ophelia Solar
IA Status
Facility Study

Ophelia Solar

BetaActiveSolarERCOTLBNL + Live

110.5 MW generation in Ector, TX · In queue since September 2022 · Proposed COD September 2028

110.5 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6 years

Facilities Study50%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-19

Project Details

State

TX

County

Ector

Region

ERCOT

Developer

Ophelia Solar

Utility

Entity

ERCOT

Point of Interconnection

Tapping the 138 kV Line from Moss Switch (Bus# 1019) to Shin Oak POD (Bus# 11128). The project has a 110 MW PUN load at the high side of the MPT (refer to the substation SLD).

Data Source

LBNL + Live

No news available for this project.