Shoshana Storage
BetaActiveBatteryERCOTLBNL + Live
221 MW storage in Matagorda, TX · In queue since March 2022 · Proposed COD May 2028
221 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 2m
Facilities Study50%
Queue EntryMar 30, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-30
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
Shoshana Storage Project LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap STP _x0013_ Refuge ckt 27
Data Source
LBNL + Live