Bronze Quinta Storage
BetaActiveBatteryERCOTLBNL + Live
103.51 MW storage in Hidalgo, TX · In queue since January 2022 · Proposed COD January 2028
103.51 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6 years
Facilities Study50%
Queue EntryJan 13, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-01
Project Details
State
TX
County
Hidalgo
Region
ERCOT
Developer
KCE TX 28, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
S_MCALLN 8371 (S. McAllen 138kV Substation)
Data Source
LBNL + Live
No news available for this project.