Bug Tussle Wind Project
ERCOT-23INR0441BetaActiveWindERCOTLBNL + Live
396.8 MW generation in Lamar, TX · In queue since January 2022 · Proposed COD September 2028
396.8 MW
Capacity
1
Components
Wind
4y 3m
In Queue
IA Executed
IA Status
Signed Jul 2024
Interconnection Timeline
Queue → IA
2y 6m
IA → COD
4y 2m
Total Duration
2y 6m
Construction75%
Queue EntryJan 13, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJul 10, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2028-09-18
Project Details
State
TX
County
Lamar
Region
ERCOT
Developer
Bug Tussle Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 1729 Valley South and 1692 Paris
Data Source
LBNL + Live
No news available for this project.