Smokey Willie Solar SLF
BetaActiveSolarERCOTLBNL + Live
200.92 MW generation in Anderson, TX · In queue since January 2022 · Proposed COD September 2028
200.92 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 8m
Facilities Study50%
Queue EntryJan 6, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
TX
County
Anderson
Region
ERCOT
Developer
Neches Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 3325 Blackburn Switch _x0013_ 3272 Palestine
Data Source
LBNL + Live
No news available for this project.