SOHO BESS
ERCOT-23INR0419BetaActiveBatteryERCOTLBNL + Live
206.32 MW storage in Brazoria, TX · In queue since December 2021 · Proposed COD June 2026
206.32 MW
Capacity
1
Components
Battery
4y 4m
In Queue
IA Executed
IA Status
Signed Dec 2022
Interconnection Timeline
Queue → IA
1 year
IA → COD
3y 6m
Total Duration
1 year
Construction75%
Queue EntryDec 3, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 1, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
ESTX-PLDHOUSTON2
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
43035 Oasis 345kV
Data Source
LBNL + Live