Sunbelt Storage
BetaActiveBatteryERCOTLBNL + Live
52 MW storage in Kaufman, TX · In queue since November 2021 · Proposed COD December 2026
52 MW
Capacity
1
Components
Battery
4y 4m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 1m
Facilities Study50%
Queue EntryNov 12, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Kaufman
Region
ERCOT
Developer
Rose Hill Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 6902 Talty - 6894 Rose Hill
Data Source
LBNL + Live
No news available for this project.