Connolly Storage
BetaSuspendedOtherERCOTLBNL
203 MW generation in Wise, TX · In queue since October 2021
203 MW
Capacity
1
Components
Other
4y 5m
In Queue
IA Executed
IA Status
Signed Feb 2023
Interconnection Timeline
Queue → IA
1y 4m
Total Duration
1y 4m
Suspended75%
Queue EntryOct 27, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 27, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–36 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Wise
Region
ERCOT
Developer
BT Connolly Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 1568 Allison – 11568 Flatwood
Data Source
LBNL
No news available for this project.