Camp Creek Solar SLF
165.6 MW generation in Robertson, TX · In queue since December 2021 · Proposed COD September 2028
165.6 MW
Capacity
1
Components
Solar
4y 4m
In Queue
IA Executed
IA Status
Signed Jul 2023
Queue → IA
1y 7m
IA → COD
5y 2m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-09-15
State
TX
County
Robertson
Region
ERCOT
Developer
White Rock Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345 KV 3400 TWIN OAK SWITCH - 46020 LIMESTONE PLANT CIRCUIT 1
Data Source
LBNL + Live