Backwater Storage
BetaActiveBatteryERCOTLBNL
100 MW storage in Cooke, TX · In queue since September 2021 · Proposed COD September 2027
100 MW
Capacity
1
Components
Battery
4y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6 years
Facilities Study50%
Queue EntrySep 17, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-15
Project Details
State
TX
County
Cooke
Region
ERCOT
Developer
Backwater Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 684 Spring - 685 Leo
Data Source
LBNL
No news available for this project.