Fronton Solar 1
BetaActiveSolarERCOTLBNL
132.7 MW generation in Starr, TX · In queue since October 2021 · Proposed COD December 2026
132.7 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 2m
Facilities Study50%
Queue EntryOct 5, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-14
Project Details
State
TX
County
Starr
Region
ERCOT
Developer
Meshek USA Inc.
Utility
—
Entity
ERCOT
Point of Interconnection
8796 Roma Substation 138kV
Data Source
LBNL