Cross Trails Storage
BetaActiveBatteryERCOTLBNL
58.29 MW storage in Scurry, TX · In queue since November 2021 · Proposed COD May 2025
58.29 MW
Capacity
1
Components
Battery
4y 4m
In Queue
IA Executed
IA Status
Signed Jul 2024
Interconnection Timeline
Queue → IA
2y 8m
IA → COD
10 months
Total Duration
2y 8m
Schedule
10 months past proposed COD
Construction75%
Queue EntryNov 3, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJul 18, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-05-26
Project Details
State
TX
County
Scurry
Region
ERCOT
Developer
Cross Trails Energy Storage Project, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
60090 WKN Breaker 69kV
Data Source
LBNL
No news available for this project.