Fewell Solar
ERCOT-23INR0367BetaActiveSolarERCOTLBNL + Live
203.5 MW generation in Limestone, TX · In queue since August 2021 · Proposed COD March 2027
203.5 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Executed
IA Status
Signed Aug 2023
Interconnection Timeline
Queue → IA
2 years
IA → COD
3y 7m
Total Duration
2 years
Construction75%
Queue EntryAug 19, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 18, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-03-15
Project Details
State
TX
County
Limestone
Region
ERCOT
Developer
Fewell Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3597 Groesbeck - 3634 Groesbeck Main
Data Source
LBNL + Live