Third Coast BESS — Project Summary

Queue ID
ERCOT-23INR0361
Capacity
102.82 MW
Technology
Battery
Status
active
Location
Jackson, TX
Region
ERCOT
Developer
Third Coast BESS LLC
IA Status
IA Executed

Third Coast BESS

ERCOT-23INR0361BetaActiveBatteryERCOTLBNL + Live

102.82 MW storage in Jackson, TX · In queue since August 2021 · Proposed COD June 2027

102.82 MW

Capacity

1

Components

Battery

4y 8m

In Queue

IA Executed

IA Status

Signed May 2023

Interconnection Timeline

Queue → IA

1y 9m

IA → COD

4y 1m

Total Duration

1y 9m

Construction75%
Queue EntryAug 24, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 17, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-06-15

Project Details

State

TX

County

Jackson

Region

ERCOT

Developer

Third Coast BESS LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

8125 Lolita substation 138kV

Data Source

LBNL + Live

Linked EIA Plant

Third Coast BESS, LLC

EIA Plant ID: 67667

View Plant
No news available for this project.