BRP Crios BESS
BetaActiveBatteryERCOTLBNL + Live
87.37 MW storage in Comanche, TX · In queue since October 2021 · Proposed COD March 2028
87.37 MW
Capacity
1
Components
Battery
4y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 5m
Facilities Study50%
Queue EntryOct 18, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
TX
County
Comanche
Region
ERCOT
Developer
BRP Crios BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 1649 HASSE_P8 - 1684 SABANA_8
Data Source
LBNL + Live
No news available for this project.