Bordertown BESS
ERCOT-23INR0354BetaActiveBatteryERCOTLBNL + Live
100 MW storage in Starr, TX · In queue since September 2021 · Proposed COD June 2027
100 MW
Capacity
1
Components
Battery
4y 7m
In Queue
IA Executed
IA Status
Signed Oct 2022
Interconnection Timeline
Queue → IA
1y 1m
IA → COD
4y 8m
Total Duration
1y 1m
Construction75%
Queue EntrySep 1, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 12, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-06-15
Project Details
State
TX
County
Starr
Region
ERCOT
Developer
Bordertown BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8796 Roma 138kV
Data Source
LBNL + Live
No news available for this project.