Blue Valley Solar
BetaActiveSolarERCOTLBNL
147.99 MW generation in Val Verde, TX · In queue since November 2021 · Proposed COD March 2028
147.99 MW
Capacity
1
Components
Solar
4y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 4m
Facilities Study50%
Queue EntryNov 16, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-15
Project Details
State
TX
County
Val Verde
Region
ERCOT
Developer
Blue Valley Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap on the 138 kV Comstock(#8683) - Corral Line(#60389)
Data Source
LBNL