Aggie Energy storage
BetaActiveBatteryERCOTLBNL
104.4 MW storage in Brazos, TX · In queue since August 2021 · Proposed COD June 2026
104.4 MW
Capacity
1
Components
Battery
4y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 10m
Facilities Study50%
Queue EntryAug 16, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-15
Project Details
State
TX
County
Brazos
Region
ERCOT
Developer
KINGFISHER ENERGY STORAGE LLC
Utility
—
Entity
ERCOT
Point of Interconnection
TABOR RD (#32882)
Data Source
LBNL
No news available for this project.