Aggie Energy storage — Project Summary

Queue ID
ERCOT-23INR0348
Capacity
104.4 MW
Technology
Battery
Status
active
Location
Brazos, TX
Region
ERCOT
Developer
KINGFISHER ENERGY STORAGE LLC
IA Status
Facility Study

Aggie Energy storage

BetaActiveBatteryERCOTLBNL

104.4 MW storage in Brazos, TX · In queue since August 2021 · Proposed COD June 2026

104.4 MW

Capacity

1

Components

Battery

4y 7m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 10m

Facilities Study50%
Queue EntryAug 16, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-15

Project Details

State

TX

County

Brazos

Region

ERCOT

Developer

KINGFISHER ENERGY STORAGE LLC

Utility

Entity

ERCOT

Point of Interconnection

TABOR RD (#32882)

Data Source

LBNL

No news available for this project.