Elmax Power Station (TEF- Due Diligence)
ERCOT-23INR0345BetaActiveGasERCOTLBNL + Live
518.83 MW generation in Harris, TX · In queue since September 2021 · Proposed COD July 2028
518.83 MW
Capacity
1
Components
Gas
4y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 10m
Facilities Study50%
Queue EntrySep 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-05
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
Elmax Generating, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Lake Houston (#40820) - Atascocita (#40130) ckt 66
Data Source
LBNL + Live
No news available for this project.