Brizo BESS
ERCOT-23INR0342BetaActiveBatteryERCOTLBNL + Live
140.76 MW storage in Victoria, TX · In queue since October 2021 · Proposed COD December 2027
140.76 MW
Capacity
1
Components
Battery
4y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 2m
Facilities Study50%
Queue EntryOct 5, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
BRP Brizo BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Loop 463 Substation (#5680)
Data Source
LBNL + Live
No news available for this project.