Larkspur Energy Storage — Project Summary

Queue ID
ERCOT-23INR0340
Capacity
307.46 MW
Technology
Battery
Status
active
Location
Upton, TX
Region
ERCOT
Developer
Larkspur Energy Storage LLC
IA Status
IA Executed

Larkspur Energy Storage

ERCOT-23INR0340BetaActiveBatteryERCOTLBNL + Live

307.46 MW storage in Upton, TX · In queue since August 2021 · Proposed COD May 2027

307.46 MW

Capacity

1

Components

Battery

4y 8m

In Queue

IA Executed

IA Status

Signed Feb 2022

Interconnection Timeline

Queue → IA

6 months

IA → COD

5y 3m

Total Duration

6 months

Construction75%
Queue EntryAug 2, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 28, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-05-05

Project Details

State

TX

County

Upton

Region

ERCOT

Developer

Larkspur Energy Storage LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

71213 Benedum 138kV

Data Source

LBNL + Live

No news available for this project.