Bypass Battery Storage
BetaActiveBatteryERCOTLBNL
207.89 MW storage in Fort Bend, TX · In queue since August 2021 · Proposed COD December 2025
207.89 MW
Capacity
1
Components
Battery
4y 7m
In Queue
IA Executed
IA Status
Signed Dec 2023
Interconnection Timeline
Queue → IA
2y 4m
IA → COD
2 years
Total Duration
2y 4m
Schedule
3 months past proposed COD
Construction75%
Queue EntryAug 18, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 4, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-12-15
Project Details
State
TX
County
Fort Bend
Region
ERCOT
Developer
Bypass BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
44000 W_A_P__POI5A 345 kV
Data Source
LBNL
No news available for this project.