Backwater Solar
BetaActiveSolarERCOTLBNL
80 MW generation in Cooke, TX · In queue since August 2021 · Proposed COD May 2027
80 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 9m
Facilities Study50%
Queue EntryAug 24, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-06
Project Details
State
TX
County
Cooke
Region
ERCOT
Developer
Backwater Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV line from Spring (#684) - Leo(#685)
Data Source
LBNL
No news available for this project.