Lumberjack Storage — Project Summary

Queue ID
ERCOT-23INR0324
Capacity
51.3 MW
Technology
Battery
Status
active
Location
Cherokee, TX
Region
ERCOT
Developer
EDP Renewables North America LLC
IA Status
IA Executed

Lumberjack Storage

ERCOT-23INR0324BetaActiveBatteryERCOTLBNL + Live

51.3 MW storage in Cherokee, TX · In queue since August 2021 · Proposed COD November 2029

51.3 MW

Capacity

1

Components

Battery

4y 8m

In Queue

IA Executed

IA Status

Signed Mar 2024

Interconnection Timeline

Queue → IA

2y 7m

IA → COD

5y 8m

Total Duration

2y 7m

Construction75%
Queue EntryAug 12, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMar 20, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2029-11-01

Project Details

State

TX

County

Cherokee

Region

ERCOT

Developer

EDP Renewables North America LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

138 kV Tap 3110 Stryker Creek - 3147 Troup

Data Source

LBNL + Live

No news available for this project.