Hofbrau BESS
BetaActiveBatteryERCOTLBNL + Live
180.72 MW storage in Tom Green, TX · In queue since September 2021 · Proposed COD July 2028
180.72 MW
Capacity
1
Components
Battery
4y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 10m
Facilities Study50%
Queue EntrySep 22, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Tom Green
Region
ERCOT
Developer
Momentum Hofbrau LLC
Utility
—
Entity
ERCOT
Point of Interconnection
6442 Redcreek 138kV
Data Source
LBNL + Live
No news available for this project.