Fowler Ranch Storage
BetaActiveBatteryERCOTLBNL + Live
26.07 MW storage in Crane, TX · In queue since June 2021 · Proposed COD June 2027
26.07 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6 years
Facilities Study50%
Queue EntryJun 21, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Crane
Region
ERCOT
Developer
Crane BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
76025 Castle Mountain 138kV
Data Source
LBNL + Live
No news available for this project.