Trojan Solar SLF — Project Summary

Queue ID
ERCOT-23INR0296
Capacity
150.59 MW
Technology
Solar
Status
active
Location
Cooke, TX
Region
ERCOT
Developer
Compadre Solar, LLC
IA Status
IA Executed

Trojan Solar SLF

ERCOT-23INR0296BetaActiveSolarERCOTLBNL + Live

150.59 MW generation in Cooke, TX · In queue since July 2021 · Proposed COD May 2026

150.59 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Executed

IA Status

Signed Oct 2022

Interconnection Timeline

Queue → IA

1y 3m

IA → COD

3y 7m

Total Duration

1y 3m

Construction75%
Queue EntryJul 1, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 10, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-05-05

Project Details

State

TX

County

Cooke

Region

ERCOT

Developer

Compadre Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

11735 Cedar Elm Switch 345kV

Data Source

LBNL + Live

No news available for this project.