Trojan Solar SLF
ERCOT-23INR0296BetaActiveSolarERCOTLBNL + Live
150.59 MW generation in Cooke, TX · In queue since July 2021 · Proposed COD May 2026
150.59 MW
Capacity
1
Components
Solar
4y 9m
In Queue
IA Executed
IA Status
Signed Oct 2022
Interconnection Timeline
Queue → IA
1y 3m
IA → COD
3y 7m
Total Duration
1y 3m
Construction75%
Queue EntryJul 1, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 10, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-05
Project Details
State
TX
County
Cooke
Region
ERCOT
Developer
Compadre Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11735 Cedar Elm Switch 345kV
Data Source
LBNL + Live