Sultan Solar
BetaActiveSolarERCOTLBNL
206.11 MW generation in Bosque, TX · In queue since July 2021 · Proposed COD December 2026
206.11 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 5m
Facilities Study50%
Queue EntryJul 1, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Bosque
Region
ERCOT
Developer
Lake Whitney Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 68080 Sam Switch _x0013_ 68090 Kopperl
Data Source
LBNL
No news available for this project.