Skull Creek Solar
137.26 MW generation in Anderson, TX · In queue since May 2021 · Proposed COD May 2027
137.26 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Status
Signed May 2024
Queue → IA
3 years
IA → COD
3 years
Total Duration
3 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-05-16
State
TX
County
Anderson
Region
ERCOT
Developer
Skull Creek Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3281 Tennessee Colony - 3499 Blackfoot Massey Lake Switch in TSP_x0019_s Pin Oak Switch - Long Lake Substation
Data Source
LBNL + Live
Last updated 2026-03-26