Kota Battery
200.6 MW storage in Carson, TX · In queue since June 2021 · Proposed COD October 2028
200.6 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
State
TX
County
Carson
Region
ERCOT
Developer
Kota Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
23900 Alibates 345kV
Data Source
LBNL + Live
$174 million South Dakota battery project signals intent to begin permitting process
If built, the project would be the first large-scale, standalone battery storage facility of its kind in the state of South Dakota.
$174 million South Dakota battery project signals intent to begin permitting process
A $174 million industrial scale battery project has filed intent to pursue a permit in South Dakota.
$174 million South Dakota battery project signals intent to begin permitting process
A $174 million industrial scale battery project has filed intent to pursue a permit in South Dakota.
$174 million South Dakota battery project signals intent to begin permitting process
Last month, utilities regulators voted 2-1 to tell a company that wants to put industrial scale batteries near Watertown that they'll need a...
Last updated 2026-03-14