Tucana BESS
BetaActiveBatteryERCOTLBNL + Live
201.3 MW storage in Andrews, TX · In queue since June 2021 · Proposed COD March 2028
201.3 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 9m
Facilities Study50%
Queue EntryJun 3, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
TX
County
Andrews
Region
ERCOT
Developer
BRP Tucana BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
1157 Andrews County South 138kV
Data Source
LBNL + Live