BRP Parana BESS — Project Summary

Queue ID
ERCOT-23INR0274
Capacity
303.67 MW
Technology
Battery
Status
active
Location
Guadalupe, TX
Region
ERCOT
Developer
BRP Parana BESS
IA Status
Facility Study

BRP Parana BESS

BetaActiveBatteryERCOTLBNL

303.67 MW storage in Guadalupe, TX · In queue since May 2021 · Proposed COD December 2025

303.67 MW

Capacity

1

Components

Battery

4y 10m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 7m

Schedule

4 months past proposed COD

Facilities Study50%
Queue EntryMay 31, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

TX

County

Guadalupe

Region

ERCOT

Developer

BRP Parana BESS

Utility

Entity

ERCOT

Point of Interconnection

7178 Marion 138kV

Data Source

LBNL

No news available for this project.