Langer Storage — Project Summary

Queue ID
ERCOT-23INR0266
Capacity
61.53 MW
Technology
Battery
Status
active
Location
Bosque, TX
Region
ERCOT
Developer
Langer Solar, LLC
IA Status
Facility Study

Langer Storage

BetaActiveBatteryERCOTLBNL

61.53 MW storage in Bosque, TX · In queue since May 2021 · Proposed COD March 2027

61.53 MW

Capacity

1

Components

Battery

4y 10m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 10m

Facilities Study50%
Queue EntryMay 10, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-01

Project Details

State

TX

County

Bosque

Region

ERCOT

Developer

Langer Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 68040 Kopperl - 68091 Navarro

Data Source

LBNL

No news available for this project.