Dodd Solar I
ERCOT-23INR0261BetaActiveSolarERCOTLBNL + Live
201.8 MW generation in Henderson, TX · In queue since June 2021 · Proposed COD June 2028
201.8 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7 years
Facilities Study50%
Queue EntryJun 24, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-05
Project Details
State
TX
County
Henderson
Region
ERCOT
Developer
Forest Grove Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 6951 Eustace Southeast Switch _x0013_ 3131 Forest Grove Switch
Data Source
LBNL + Live
No news available for this project.