Flatland Solar Project
BetaActiveSolarERCOTLBNL
182.2 MW generation in Scurry, TX · In queue since May 2021 · Proposed COD December 2025
182.2 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 7m
Schedule
3 months past proposed COD
Facilities Study50%
Queue EntryMay 10, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
TX
County
Scurry
Region
ERCOT
Developer
Flatland Solar Project, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
11319 Scurry County 138kV
Data Source
LBNL