Hoyte Solar
ERCOT-23INR0235BetaActiveSolarERCOTLBNL + Live
206.75 MW generation in Milam, TX · In queue since April 2021 · Proposed COD April 2027
206.75 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
Signed Oct 2022
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
4y 6m
Total Duration
1y 6m
Construction75%
Queue EntryApr 1, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 14, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-04-15
Project Details
State
TX
County
Milam
Region
ERCOT
Developer
Milano Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(3707) Cannon Switch 138kV
Data Source
LBNL + Live
No news available for this project.