Chiltepin Solar
BetaActiveSolarERCOTLBNL
200 MW generation in Reeves, TX · In queue since April 2021 · Proposed COD June 2025
200 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 2m
Schedule
9 months past proposed COD
Facilities Study50%
Queue EntryApr 22, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-30
Project Details
State
TX
County
Reeves
Region
ERCOT
Developer
Chiltepin Solar-Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
6673 Musquiz 138kV
Data Source
LBNL
No news available for this project.