Chiltepin Solar — Project Summary

Queue ID
ERCOT-23INR0234
Capacity
200 MW
Technology
Solar
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
Chiltepin Solar-Storage, LLC
IA Status
Facility Study

Chiltepin Solar

BetaActiveSolarERCOTLBNL

200 MW generation in Reeves, TX · In queue since April 2021 · Proposed COD June 2025

200 MW

Capacity

1

Components

Solar

4y 11m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 2m

Schedule

9 months past proposed COD

Facilities Study50%
Queue EntryApr 22, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-30

Project Details

State

TX

County

Reeves

Region

ERCOT

Developer

Chiltepin Solar-Storage, LLC

Utility

Entity

ERCOT

Point of Interconnection

6673 Musquiz 138kV

Data Source

LBNL