Earthwise Solar
BetaActiveSolarERCOTLBNL + Live
370.5 MW generation in Hardeman, TX · In queue since March 2022 · Proposed COD December 2028
370.5 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 9m
Facilities Study50%
Queue EntryMar 14, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
TX
County
Hardeman
Region
ERCOT
Developer
Quanah Solar 2
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 60504 Tesla - 61001 Jim Treece
Data Source
LBNL + Live
No news available for this project.