Rocinante BESS
ERCOT-23INR0232BetaActiveBatteryERCOTLBNL + Live
33.17 MW storage in Gonzales, TX · Proposed COD March 2027
33.17 MW
Capacity
1
Components
Battery
—
In Queue
—
IA Status
Signed Apr 2022
Interconnection Timeline
IA → COD
4y 11m
Construction0%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 25, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-03-16
Project Details
State
TX
County
Gonzales
Region
ERCOT
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live
No news available for this project.