Maleza Solar II
BetaActiveSolarERCOTLBNL + Live
254.94 MW generation in Wharton, TX · In queue since April 2021 · Proposed COD December 2028
254.94 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 8m
Facilities Study50%
Queue EntryApr 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
Brush Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap Blue _x0013_ Hillje 345 kv Ckt.#27
Data Source
LBNL + Live
No news available for this project.