Morning Glory Solar — Project Summary

Queue ID
ERCOT-23INR0224
Capacity
122.4 MW
Technology
Solar
Status
active
Location
Tom Green, TX
Region
ERCOT
Developer
Armadillo Solar, LLC
IA Status
Facility Study

Morning Glory Solar

BetaActiveSolarERCOTLBNL + Live

122.4 MW generation in Tom Green, TX · In queue since June 2021 · Proposed COD March 2026

122.4 MW

Capacity

1

Components

Solar

4y 9m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 9m

Facilities Study50%
Queue EntryJun 16, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

TX

County

Tom Green

Region

ERCOT

Developer

Armadillo Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 7077 Amos Creek - 76009 Twin Buttes

Data Source

LBNL + Live

No news available for this project.