Dogfish BESS — Project Summary

Queue ID
ERCOT-23INR0219
Capacity
78.2 MW
Technology
Battery
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
Dogfish ESS Assets, LLC
IA Status
IA Executed

Dogfish BESS

BetaActiveBatteryERCOTLBNL

78.2 MW storage in Pecos, TX · In queue since March 2021 · Proposed COD April 2025

78.2 MW

Capacity

1

Components

Battery

5 years

In Queue

IA Executed

IA Status

Signed Jun 2023

Interconnection Timeline

Queue → IA

2y 3m

IA → COD

1y 10m

Total Duration

2y 3m

Schedule

11 months past proposed COD

Construction75%
Queue EntryMar 16, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 1, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-04-16

Project Details

State

TX

County

Pecos

Region

ERCOT

Developer

Dogfish ESS Assets, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 138kV 38331 TN Alamo St _x0013_ 38455 TN Holiday

Data Source

LBNL

No news available for this project.