El Patrimonio Solar
ERCOT-23INR0207BetaActiveSolarERCOTLBNL + Live
152.32 MW generation in Bexar, TX · In queue since March 2021 · Proposed COD April 2027
152.32 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Status
Signed Dec 2023
Interconnection Timeline
Queue → IA
2y 9m
IA → COD
3y 4m
Total Duration
2y 9m
Construction75%
Queue EntryMar 16, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 11, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-04-29
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
Heritage Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 5429 Trumbo - 5260 Leon Creek
Data Source
LBNL + Live
No news available for this project.